header-left
File #: 2007-0438    Version: Name: 153rd Street Watermain - Proposal
Type: MOTION Status: PASSED
File created: 7/5/2007 In control: Board of Trustees
On agenda: 7/16/2007 Final action: 7/16/2007
Title: 153rd Street Watermain - Proposal

Title

153rd Street Watermain - Proposal

History

In the course of the ongoing 153rd Street Reconstruction and Widening Project at the new Park Station Boulevard entrance into the Cherry Hill Subdivision, the 36” distribution watermain was found to be significantly more shallow than anticipated.  While excavating the new roadway, the top of the watermain was found to be only 6” below the rough excavation and 30” below the finish street elevation.  A minimum depth of 5’ is needed to cover a watermain. 

 

This major distribution main runs along 153rd Street in an adjacent easement on the south side of the street and services the entire western portion of the Village.

 

To ensure appropriate cover is maintained, the design engineer (Christopher B. Burke Engineering Ltd.) was asked to submit a revised grading profile to the Cook County Highway Department.  This re-engineering resulted in an additional 14” of cover on the watermain.  To implement these changes, the cost for this additional work will be $25,000.

 

The additional cover needed to obtain the minimum 5’ depth will be achieved by lowering the watermain in place.  Airy’s, Inc. of Tinley Park, Illinois, was asked to provide a proposal for this specialized and difficult challenge.  Their proposal totals $60,087 to complete the work in one 16-hour day.  Because of the nature of this work, a contingency is requested totaling $9,913.

 

Due to the emergency nature of this work and potential for catastrophic failure, it is requested that the bid process be waived.  This work will be accomplished at the earliest possible time based on weather conditions and water demand.

 

On July 9, 2007, this item was reviewed and approved by the Public Works and Engineering Committee and referred to the Board for approval.

 

INFORMATION PREVIOUSLY PROVIDED AS PART OF THE JULY 9, 2007, PUBLIC WORKS AND ENGINEERING COMMITTEE PACKET.

 

Financial Impact

Funds are available in the Underground Water and Sewer Account #031-6004-433.70-50 to cover this emergency expense.

 

Recommended Action/Motion

I move to approve authorizing the Village Manager to amend the Intergovernmental Agreement with Cook County to include the payment of $25,000 for the additional road work necessary to provide cover for the 36” distribution watermain;

 

And

 

Approve authorizing payment to Cook County for the road work necessary to cover the existing watermain in an amount not to exceed $25,000;

 

And

 

Approve waiving the bidding process for the lowering of the 153rd Street 36” watermain;

 

And

 

Approve accepting the proposal from Airy’s, Inc. of Tinley Park, Illinois,

for the lowering of 153rd Street 36” watermain in an amount not to exceed $70,000;

 

And

 

Approve authorizing the Village Manager to execute the proposal/contract.