File #: 2011-0469    Version: Name: Catalina Stormwater Improvements - Preliminary Engineering Design Services
Type: MOTION Status: IN BOARD OF TRUSTEES
File created: 7/12/2011 In control: Board of Trustees
On agenda: 7/31/2011 Final action: 7/31/2011
Title: Catalina Stormwater Improvements - Preliminary Engineering Design Services
Attachments: 1. PROPOSAL CATALINA STORMWATER IMPROVEMENT, 2. Signed Catalina Stormwater contract.pdf

Title

Catalina Stormwater Improvements - Preliminary Engineering Design Services

 

History

The Catalina Subdivision has a history of stormwater related complaints.  The general design for this 1970’s era development included a stormwater management and detention design that utilized streets and cul-de-sacs within the development for the temporary storage of stormwater when rains were of such intensity that the runoff was in excess of the piped-system capacity.  This “ponding” is seen by the residents of Catalina as “flooding.”

 

Over the past decade, a comprehensive flood survey was performed within the Village to address and correct significant known chronic flooding, and today much has been accomplished to eliminate chronic flooding that has caused repeated property damage.  During this same period, the residents of Catalina continued to press their case for relief from the street ponding that they continued to view as flooding.  Staff is aware that during two recent intense events minor water did enter less than five homes in Catalina, attributed in large part to residential landscaping changes.  With the event of June 6, 2011, several homes came perilously close to having significant water enter their homes as the street “ponds” had no remaining capacity. 

 

It is agreed by staff and the Village’s Engineer that the street ponding that occurs within Catalina is consistent with the approved design, and generally functions very well as homes within the development do not flood.  It is also acknowledged that residents do have an expectation that they be allowed to arrive and leave their homes during and immediately after heavy rains and see the ponding as flooding.  With the street ponding design utilized for Catalina, free access to many homes is not possible as the streets and cul-de-sacs by design retain water for several hours following heavy rains.

 

In October 2010, staff met with representatives of Commonwealth Edison to confirm the ability to utilize the area beneath the high tension transmission towers as a stormwater detention facility.  Subsequently, staff requested that Christopher B. Burke Engineering Ltd. (CBBEL) of Rosemont, Illinois (the Village’s Engineer), submit a scope and fee proposal to provide preliminary engineering to examine the feasibility and work required to retro-fit the Catalina stormwater conveyance system to permit stormwater to be freely conveyed to an off-site detention facility. 

 

Staff has reviewed the June 14, 2011, proposal from CBBEL and finds it to be of good value for the scope of work to be performed.  This effort will determine the size and location of the off-site storage facility required to eliminate the current street storage of stormwater, will provide a means for stormwater to get to and from the new storage facility, and will develop a probable cost for the final improvement. 

 

On July 18, 2011, this item was reviewed and approved by the Public Works and Engineering Committee and referred to the Board for approval.

 

INFORMATION PREVIOUSLY PROVIDED AS PART OF THE JULY 18, 2011, PUBLIC WORKS AND ENGINEERING COMMITTEE PACKET.

 

Financial Impact

Funds are available within the approved 2011 Capital Budget 031-6007-433.32-50 to provide for the work required for this Preliminary Engineering effort.

 

Recommended Action/Motion

I move to approve awarding a contract to Christopher B. Burke Engineering Ltd. of Rosemont, Illinois, for Professional Engineering Services as outlined in their June 14, 2011, proposal for preliminary engineering to provide conveyance and off-site detention of stormwater for the Catalina Subdivision in an amount not to exceed $9,500.