File #: 2013-0322    Version: Name: Unincorporated Palos and Orland Township Stormwater Infrastructure Maintenance Responsibility Evaluation
Type: MOTION Status: PASSED
File created: 5/16/2013 In control: Board of Trustees
On agenda: 6/3/2013 Final action: 6/3/2013
Title: Unincorporated Palos and Orland Township Stormwater Infrastructure Maintenance Responsibility Evaluation
Attachments: 1. Contract - Christopher B. Burke Engineering, 2. Proposal

Title

Unincorporated Palos and Orland Township Stormwater Infrastructure Maintenance Responsibility Evaluation

 

History

In the late 1970s the Village of Orland Park entered into an agreement to provide water and sanitary sewer service to unincorporated portions of Palos Township.  Since that time several additional developments outside Village boundaries in both Palos and Orland Township have been added to the water and sanitary sewer system.  The Village has always taken a position of responsibility for only the sanitary and water systems.  It was the Village’s position that the storm water system (except for the Mill Creek pond) was the responsibility of the township. 

 

All permitting for the sanitary and storm systems are managed by the Metropolitan Water reclamation District (MWRD).  After extensive legal discussion pertaining to three specific projects it has been concluded that the Village is also required to maintain their respective storm systems as co-permittee under MWRD ordinances.  Based on this decision it is anticipated that responsibility for the remainder of the storm systems in Orland and Palos Township, built under MWRD permit to the Village, will be the responsibility of the Village.  Although there is no pending enforcement action by the MWRD, Village staff recommends that an engineering evaluation of the stormwater area be completed to better determine the current status and repair of the system.

 

To get a clear understanding of the magnitude of this undertaking and the potential costs involved with the maintenance, Christopher B. Burke Engineering, Ltd. of Rosemont, Illinois (CBBEL) has submitted a proposal.  The initial phase will involve researching each permit to clarify responsibility.  At the same time, where Village responsibility is confirmed, storm infrastructure quantities will be obtained to help establish future maintenance costs.  The proposal for the defined work is $7,200.

 

Future phases of this project will include cursory inspections to determine current condition and establish expected maintenance costs and the final phase to provide potential funding source options to maintain the systems, should it be mandated on the village. 

 

On May 20, 2013, this item was reviewed by the Public Works and Engineering Committee, recommended for approval and referred to the Village Board of Trustees for consideration.

 

Financial Impact

Funds for this phase are available in Account #031-6001-432500 Engineering Services.

 

Recommended Action/Motion

I move to approve accepting the proposal from Christopher B. Burke Engineering, Ltd. of Rosemont, Illinois, for the Evaluation of Storm water Infrastructure Maintenance Responsibilities for Portions of Unincorporated Palos and Orland Township in an amount not to exceed $7,200.