File #: 2023-0394    Version: 0 Name: STP Phase I Engineering - 143rd Street, 131st Street, and Orland Parkway - Proposals
Type: MOTION Status: PASSED
File created: 5/8/2023 In control: Board of Trustees
On agenda: 6/19/2023 Final action: 6/19/2023
Title: /Name/Summary STP Phase I Engineering - 143rd Street, 131st Street, and Orland Parkway - Proposals
Attachments: 1. Phase I Scope of Services, 2. Proposal - B&W - Orland Pkwy, 3. Proposal - B&W -131st St, 4. Proposal - B&W -143rd St, 5. Proposal - ERA -131stSt, 6. Proposal - V3, 7. V3 Companies of Illinois, LTD - STP Phase l ENG for 143rd, 131st and Orland Parkway, 8. V3 Companies of Illinois - CO#1 for STP Phase l Design - 143rd St 131st St & Orland Parkway, 9. V3 Companies of Illinois - Addendum A for STP Phase l Design for 143rd, 131st & Orland Parkway

Title/Name/Summary

STP Phase I Engineering - 143rd Street, 131st Street, and Orland Parkway - Proposals

 

History

143rd Street, 131st Street, and Orland Parkway are formerly referred to as FAU (Federal Aid Urban) routes, and they fall under the Village’s maintenance jurisdiction. They are eligible for federal funding through the Southwest Conference of Mayors Surface Transportation Program (STP) due to their functional classifications. 

 

Due to their age and the amount of daily traffic, the pavement surface on these streets is deteriorating and will need to be resurfaced in the near future. Resurfacing these roads along with ADA mobility improvements are anticipated within the next few years. The cost of construction and Phase III construction oversight are eligible for federal financial assistance. However, in order to accelerate the process for federal construction funding, the Village must complete Phase I preliminary design engineering, and have Phase II final engineering under contract for the application process.

 

The application process for federal funding is administered through the Southwest Conference of Mayors. The next call for projects will begin in January 2024. In order to prepare these projects for the January submission, staff has requested proposals for Phase I engineering services. The project limits for:

- 143rd Street - John Humphrey Drive to Harlem Avenue

- 131st Street - LaGrange Road to Southwest Highway

- Orland Parkway - Wolf Road to LaGrange Road

 

Separate proposals for each roadway were requested from the Village’s prequalified list of consulting engineering firms. The request was made to nine (9) firms: Baxter & Woodman, Inc. (B&W), Christopher B. Burke Engineering, Ltd. (CBBEL), HR Green, Inc. (HRG), V3 Companies (V3); Jacobs Engineering (JE), Ciorba Group (CG), CivliTech Inc. (CTI), Engineering Resource Associates (ERA), and TransSystems (TS). Three (3) firms submitted proposals, three (3) firms respectfully declined submitting, and three (3) firms did not respond. The proposal costs are as follows: 

 

Firm - 131st Street / 143rd Street / Orland Parkway

B&W - $35,680.00 / $56,605.00 / $51,540.00

ERA -  $30,902.35 / Declined / Declined

V3 - $25,832.00 / $32,940.00 / $31,408.00

 

V3 Companies is identified as the lowest cost proposer for each road, and is a firm that has established a proficient and professional relationship with the Village for several years. As such, staff recommends accepting the proposal for Phase I engineering from V3 Companies of Woodridge, Illinois in an amount not to exceed $25,832.00 for 131st Street, $32,940.00 for 143rd Street, and $31,408.00 for Orland Parkway.

 

Financial Impact

Funds for this professional engineering service are available in the Capital Improvement 3008020-432500, and is below the budget of $33,333.33 for each roadway.

 

Recommended Action/Motion

I move to approve the proposals from V3 Companies of Woodridge, Illinois for the STP Phase I Engineering for an amount not to exceed $25,832.00 for 131st Street, $32,940.00 for 143rd Street, and $31,408.00 for Orland Parkway;

 

AND

 

Authorize the Village Manager to execute all related contracts, subject to Village Attorney review.