Title
Main Pump Station - Generator Replacement - Proposal
History
A Request for Proposal was drafted by our Engineer (Greeley and Hansen LLC (G&H) of Chicago, Illinois) for the replacement of the Main Pump Station generator that failed on January 26, 2009. Two generator suppliers were identified that met the criteria as established by G&H and Village staff. To ensure equitable comparisons, two mechanical contractors were requested to work with each supplier and provide installation pricing. One generator supplier also submitted a proposal acting as the contractor. A pre-proposal meeting was held onsite at the Main Pump Station on June 12, 2009.
The proposals submitted are as follows:
Meccon Industries, Inc. of Lansing, Illinois
With Caterpillar Generator $203,200
With Katolight Generator $178,000
Genco Industries, Inc. of Crestwood, Illinois
With Caterpillar Generator $247,190
With Katolight Generator $247,190
Charles Equipment Energy Systems of Addison, Illinois
With Katolight Generator $179,000
Greeley and Hansen and Village staff have reviewed the proposals and recommend accepting the proposal from Meccon Industries, Inc. utilizing the Katolight Generator (lead-time of 10-12 weeks).
Engineering for Phase II of this project including the fire protection system is being finalized. Requests for Proposal will be obtained within the next month.
On July 13, 2009, this item was reviewed and approved by the Public Works and Engineering Committee and referred to the Board for approval.
INFORMATION PREVIOUSLY PROVIDED AS PART OF THE JULY 13, 2009, PUBLIC WORKS AND ENGINEERING COMMITTEE PACKET.
Financial Impact
There are sufficient funds available in the Water and Sewer Capital Fund 031-6002-433.70-60 to cover the cost of this replacement.
Recommended Action/Motion
I move to approve waiving the bid process;
And
Approve accepting the proposal from Meccon Industries, Inc. of Lansing, Illinois, for the Main Pump Station generator replacement for an amount not to exceed $190,000 ($178,000 plus $12,000 contingency);
And
Approve authorizing the Village Manager to execute the proposal/contract.