File #: 2008-0027    Version: Name: 108th Avenue and 159th Street Watermain Abandonment- Proposal
Type: MOTION Status: IN BOARD OF TRUSTEES
File created: 1/10/2008 In control: Board of Trustees
On agenda: 1/21/2008 Final action: 1/21/2008
Title: 108th Avenue and 159th Street Watermain Abandonment- Proposal

Title

108th Avenue and 159th Street Watermain Abandonment- Proposal

History

During the course of the 108th Avenue roadway reconstruction, the watermain at the intersection of 159th Street was found to be in conflict.  Because of the grade changes for the new pavement, the existing watermain will be too shallow.  Based on the existing watermain configuration, this main can be abandoned without detriment to our system. 

 

So as not to impact progress of the road reconstruction project, proposals were obtained to allow the work to be done immediately while the job is shut down for the winter.  An alternate price was also requested to replace an existing adjacent valve box with a valve vault if site conditions/utilities allow. 

 

Airy’s, Inc. of Tinley Park, Illinois, submitted a proposal for $10,327 plus $4,588 (alternate) for a total of $14,915.  DiPaolo Construction Company of Calumet Park, Illinois, submitted a proposal of $15,885 plus $2,755 (alternate) for a total of $18,640.  Therefore, staff recommends accepting the proposal from Airy’s, Inc. of Tinley Park, Illinois, for an amount not to exceed $14,915.

 

On January 14, 2008, this item was reviewed and approved by the Public Works and Engineering Committee and referred to the Board for approval.

 

INFORMATION PREVIOUSLY PROVIDED AS PART OF THE JANUARY 14, 2008, PUBLIC WORKS AND ENGINEERING COMMITTEE PACKET.

 

Financial Impact

Sufficient funds are available in the Underground Water Lines Account #031-6002-433.70-50 to cover the cost of this work.

 

Recommended Action/Motion

I move to approve waiving the bidding process;

 

And

 

Approve accepting the proposal from Airy’s, Inc. of Tinley Park, Illinois, for the 108th Avenue and 159th Street watermain abandonment and possible valve vault installation for an amount not to exceed $14,915;

 

And

 

Approve authorizing the Acting Village Manager to execute the proposal/contract.