header-left
File #: 2010-0232    Version: Name: Bid Award for the Thistlewood Pump House Roof Replacement
Type: MOTION Status: PASSED
File created: 5/11/2010 In control: Board of Trustees
On agenda: 6/7/2010 Final action: 6/7/2010
Title: Bid Award for the Thistlewood Pump House Roof Replacement
Attachments: 1. Thistlewood Bid Summary, 2. Ridgewood Roofing Co

Title

Bid Award for the Thistlewood Pump House Roof Replacement

 

History

Bids were received on May 6, 2010, 11:00 am in the Village Clerk’s Office for the Thistlewood Pump House Roof Replacement. Six bids were received. Ridgeworth Roofing Co., Inc. of Bridgeview was the low bidder for a cost not to exceed $52,685.00. The water department budgeted $100,000.00 for such work and the remaining will go to replacing some soffit and siding work later in the year. On May 17, 2010, this item was reviewed and approved by the Parks, Recreation & Environmental Initiatives Committee and referred to the Board for approval.

 

Financial Impact

Funds will come from the Public Works budgeted amount of $100,000.00 (P.O. # 50204).

 

Recommended Action/Motion

I move to approve Ridgeworth Roofing Co. Inc. for the Thistlewood Roof Replacement at a cost not to exceed $52,685.00.

 

And

 

To authorize the Village Manager execute the contract.