File #: 2013-0404    Version: 0 Name: EPI Contract Change Order
Type: MOTION Status: PASSED
File created: 6/13/2013 In control: Board of Trustees
On agenda: 7/1/2013 Final action: 7/1/2013
Title: EPI Contract Change Order
Attachments: 1. Invoices

Title

EPI Contract Change Order

 

History

The Cook County Department of Environmental Control requested further inspections and testing of the asbestos at the Orland Park Plaza prior to demolition. EPI (Environmental Protection Industries, our contractor) was required to return and test in a few areas. All areas have now been approved for demolition.

 

This agenda item is being considered by the Parks & Recreation Committee and the Village Board of Trustees on the same night.

 

Financial Impact

The funds will come from the Capital Land & Land Improvements account, 282-0000-470700.

 

Recommended Action/Motion

I move to approve accepting the extra work from EPI at a cost not to exceed $6,120.00.