Title
Creekside North Storm Water Improvement - Phase II Engineering Proposal
History
The Creekside North study area was part of the original Flood Study conducted by Christopher B. Burke Engineering, Ltd. (CBBEL) of Rosemont, Illinois. Phase I engineering has previously been completed. This area, near Creek Crossing Drive and Stockton Lane, has been subject to rear yard and overland flow issues impacting several homes. To advance this project, a phase II engineering proposal was requested from CBBEL.
On November 19th, 2014 the proposal for Creekside North Storm Water Improvements (Phase II Engineering) was received from CBBEL for a total cost of $94,600.00. The Phase II engineering will include additional topographic surveying, Preliminary and final engineering, Utility coordination, hydrologic and hydraulic modeling, easement coordination, permitting and bid assistance.
On December 1, 2014, this item was reviewed and approved by the Public Works Committee and referred to the Board for approval.
Financial Impact
There are sufficient funds in the FY14 Water Fund Capital Budget account 031-6007-470500 for this project.
Recommended Action/Motion
I move to approve accepting the proposal from Christopher B. Burke Engineering, Ltd. of Rosemont, Illinois for Creekside North Storm Water Improvement Phase II Engineering in an amount not to exceed $94,600.