header-left
File #: 2024-0854    Version: 0 Name: Village Hall HVAC Improvement Project - Phase 1 - Final Approval Trane Turnkey- VH Boiler
Type: MOTION Status: IN BOARD OF TRUSTEES
File created: 11/11/2024 In control: Board of Trustees
On agenda: 12/2/2024 Final action:
Title: Village Hall HVAC Improvement Project - Phase 1 - Final Approval
Attachments: 1. Board Report 2024-0331, 2. Proposal - Trane VH, 3. Sample 3rd Party Review Letter
Title
Village Hall HVAC Improvement Project - Phase 1 - Final Approval

History
On May 6, 2024, the Village Board of Trustees approved a Letter of Commitment (LOC) with Trane, Inc. (Trane) for the Village Hall HVAC Improvement Project - Phase 1. The LOC authorized Trane to move to the Proposal Stage in which Trane would complete a full set of project design plans and provide the Village with a cost proposal not to exceed $440,000.00 for the execution of those plans. Phase 1 of this project includes the replacement of the two (2) existing boilers at Village Hall, while Phase 2 will focus on the replacement of Roof Top Units (RTUs) and other HVAC improvements. Pricing for this project is in accordance with OMNIA Cooperative Contract #3341.

The Public Works Department subsequently worked with engineers from Trane to refine the scope of work, optimize the project budget and finalize project design plans. The project scope of work, a summary of which is attached, includes the replacement of the two (2) existing boilers with high efficiency condensing boilers and associated mechanical equipment. The existing boilers, which are original to the building and provide the main source of heat for Village Hall, are beyond their American Society of Heating and Air-Conditioning Engineers (ASHRAE) serviceable life expectancy. Ongoing use of the boilers will result in further decreased efficiency and reliability, and increased repair costs.

As Trane would act as the project engineer and general contractor, the scope of work includes full construction management, mechanical/electrical/structural engineering, installation and subcontracting, material shipping and storage, and a one (1) year labor and materials warranty.

Upon completion of the project plans, which are attached for reference, the final proposal price submitted by Trane, Inc. was $419,875.00, or $20,125.00 less than the original cost estimate. The cost reduction is a result of project efficiencies identified by P...