File #: 2025-0864    Version: 0 Name: Village Hall HVAC Improvement Project - Phase 2 - Final Approval
Type: MOTION Status: IN COMMITTEE /COMMISSION
File created: 10/24/2025 In control: Committee of the Whole
On agenda: 11/3/2025 Final action:
Title: Village Hall HVAC Improvement Project - Phase 2 - Final Approval
Attachments: 1. Proposal - Trane, 2. Sole Source Request Form
Title
Village Hall HVAC Improvement Project - Phase 2 - Final Approval

History
On March 17, 2025, the Village Board of Trustees approved a Letter of Commitment (LOC) with Trane, Inc. (Trane) for the Village Hall HVAC Improvement Project - Phase 2. The LOC authorized Trane to move to the Proposal Stage, in which Trane would complete a full set of project design plans and provide the Village with a cost proposal not to exceed $3,540,000.00 for the execution of those plans in 2026. Pricing for this project was in accordance with OMNIA Cooperative Contract #3341.

The Public Works Department subsequently worked with engineers from Trane to refine the scope of work, optimize the project budget and finalize project design plans. The project scope of work, which is attached for reference, includes the removal of the four (4) existing Village Hall roof top units and variable air volume (VAV) boxes, followed by the installation of new two (2) air-cooled chillers, two (2) air handling units, and fifty-four (54) VAV boxes, as well as all associated electrical, mechanical, control, testing and balancing, commissioning, and site work.

As Trane would act as the project engineer and general contractor, the scope of work also includes full construction management, mechanical/electrical/structural engineering, material shipping and storage, and a one (1) year labor and materials warranty.

Upon completion of the project plans, which are attached for reference, the final proposal price submitted by Trane, Inc. is $3,497,795.00, or $42,205.00 less than the original cost estimate. The cost reduction is a result of project efficiencies identified by Public Works Staff and a competitive internal bidding process by Trane. As previously mentioned, proposal pricing is based on OMNIA Cooperative Contract #3341. It should be noted that the Village may request a third-party review of the proposal to ensure the Trane proposal is in accordance with OMNIA Cooperative Contract Pricing Guide...