File #: 2009-0276    Version: Name: 104th Avenue - 159th Street to 167th Street Improvements - Board Approval
Type: MOTION Status: PASSED
File created: 6/3/2009 In control: Board of Trustees
On agenda: 6/15/2009 Final action: 6/15/2009
Title: 104th Avenue - 159th Street to 167th Street Improvements - Board Approval
Attachments: 1. 104 159 to 167 STREET IMPROVE 06 08 09

Title

104th Avenue - 159th Street to 167th Street Improvements - Board Approval

History

On January 19, 2009, the Board of Trustees approved a supplemental agreement with the Cook County Highway Department for additional design and geotechnical engineering on 104th Avenue.  At that time, the Board approved the Village’s portion ($15,299) but I neglected to include the portion that should be funded upfront by the Village and will be reimbursed by the County which is explained in the Village Manager’s letter to the County.  Therefore, I am requesting approval for additional funds in the amount of $65,266 to increase the purchase order for McDonough and Associates for the requested engineering in the amount of $80,565.

 

On June 8, 2009, this item was reviewed and approved by the Public Works and Engineering Committee and referred to the Board for approval.

 

INFORMATION PREVIOUSLY PROVIDED AS PART OF THE JUNE 8, 2009, PUBLIC WORKS AND ENGINEERING COMMITTEE PACKET.

 

Financial Impact

The engineering for this project totaled $80,565.  The Village’s portion is $15,299 - the remainder of $65,266 will be reimbursed by the County.

 

Recommended Action/Motion

I move to approve the additional design and geotechnical engineering for the street improvements of 104th Avenue (159th Street to 167th Street) for an amount not to exceed $65,266 to be reimbursed by the County.