header-left
File #: 2013-0130    Version: Name: Stellwagen Farm Perimeter Path and Parking Facilities
Type: MOTION Status: PASSED
File created: 2/21/2013 In control: Board of Trustees
On agenda: 6/3/2013 Final action: 6/3/2013
Title: /Name/Summary Stellwagen Farm Perimeter Path and Parking Facilities
Attachments: 1. Christopher B. Burke Engineering - Contract 2013, 2. Stellwagen Master Plan, 3. CBBEL Proposal
Title/Name/Summary
Stellwagen Farm Perimeter Path and Parking Facilities

History
QUICKFACTS
Stellwagen Farm Perimeter Path and Parking Facilities

Purpose
Design and engineering for a perimeter bike path and parking facilities to serve the Stellwagen Family Farm.

Requested Actions: Approval of Design and Engineering Contract for Christopher B. Burke Engineering Ltd. (CBBEL)

OVERVIEW AND BACKGROUND
The 2013 capital improvement budget included consideration for the design and construction of a perimeter path and parking lot for Stellwagen Farm. The Village is anticipating increased public use of this facility now that the Stellwagen life estate is approaching expiration. As part of this project, the Village, through its consulting engineer, CBBEL, submitted an IDNR Illinois Bicycle Path (IBP) grant application that could fund part of the path construction. Although results of the grant application are not yet available, it makes sense to pursue design and engineering in order to be prepared for construction when funding is available.

The IBP grant provides a maximum funding amount of $200,000, and will only fund the actual construction of the path. The total construction cost is estimated at $481,488.57. Bike path construction could occur as early as 2014, depending on IPB grant award and funding availability.

Construction of the parking lot that is planned for the area north of the farmstead is not included in the grant application. Parking lot construction is not anticipated in the near future. However, since the bike path will require permitting along 108th Avenue, it is sensible to include design and engineering work for the parking lot with the bike path to submit as a package to Cook County and obtain the necessary permits for access points to 108th Avenue.

PROJECT DESCRIPTION & CONTEXT
The CBBEL proposal-included for review-- will begin the design and engineering work for the Stellwagen Farm perimeter path in anticipation of construction star...