Title
Orland Park Bike Trail - Change Order
History
Attached is a Change Order for the Orland Park Bike Trail from Matthew Paving, Inc., as per Hitchcock Design Group. The Orland Park Bike Trail is currently under construction for needed additions through the wetlands just west of 88th Avenue. During the installation we encountered critically bad soils. The poor soil was unforeseen; however, there was a line item in the bid for this type of extra work. In order to make the path stable we have excavated 6' to 8' of the soils in this area and replaced it with large stone, creating a proper base.
Financial Impact
A budget adjustment is needed to the Parks Fund to complete this project in the amount of $105,625.00 to Account No. 023-4004-451-7080.
Recommended Action/Motion
I move to approve accepting the Change Order from Matthew Paving, Inc. for the Orland Park Bike Trail in an amount not to exceed $105,625.00;
And
I move to approve a budget adjustment in an amount not to exceed $105,625.00.