Title: Police Department Firing Range and Emergency Operations Center Facility
Attachments: 1. Staff Report to the Board of Trustees, 2. Plat of Consolidation - FINAL, 3. Engineering Plan - FINAL, 4. Landscape Plan - FINAL, 5. Site Plan - FINAL, 6. Exterior Rendering, 7. North South Elevations, 8. East West Elevations, 9. Staff Report to the Plan Commission
Title
Police Department Firing Range and Emergency Operations Center Facility

History
Project: 2023-0508 - Police Department Firing Range and EOC Facility
Petitioner: Joel Van Essen, Director of Public Works
Purpose: The petitioner is seeking approval of a plat of consolidation, site plan, landscape plan, engineering plan, and building elevations.
Location: 10609 and 10629 163rd Place
P.I.N.: 27-20-409-007-0000 and 27-20-409-008-0000
Parcel Size: 2.02 acres

SUMMARY
The petitioner is seeking approval of a plat of consolidation, site plan, landscape plan, and building elevations to construct a 15,400 square foot Firing Range and Emergency Operations Center (EOC) Facility for the Orland Park Police Department.
The subject site is within the Manufacturing zoning district (MFG) and will remain unchanged in the proposed plan, as governmental uses are permitted in the MFG district. The site is currently vacant and has a gross area of 2.02 acres. The plan proposes to consolidate the two existing parcels into one single parcel and construct a new 15,400 square-foot building. The main entrance of the building is located on the east side of the site and can be accessed through the east parking lot. The west parking lot is a secured lot used for storage vehicles seized by the police department. Within the secured lot, there is access to a garage door in the rear of the building. Additionally, there is a supply garage and a carport used for Emergency Services & Disaster Agency (ESDA) vehicles in the secured parking lot.

PLAN COMMISSION DISCUSSION
Present at the Plan Commission were 6 commissioners, the petitioner, project representatives, and members of staff. No members of the public were in attendance for the meeting. The commissioners had questions about proposed signage being in the motion, the existing detention pond to the east, underground stormwater storage, and surrounding properties.

While there is no signage proposed for the Firing Range and EOC facility, t...