Christopher B. Burke Engineering, LTD Change Order #1 and Contract Amendment A
History
On October 7, 2024, the Village Board approved awarding a contract (Legistar #2024-0736) to Christopher B. Burke Engineering, LTD (CBBEL) to develop and provide construction and engineering documents to retain a general contractor for the projects at a cost not to exceed $238,490.
This includes tasks 1 - 12 in the attached Work Effort and Free Structure, dated October 4, 2024.
The Village was awarded a $600,000 Open Space Lands Acquisition Development (OSLAD) grant in support of this redevelopment.
Village and CBBEL staff have collectively worked to develop a redevelopment plan.
On April 21, 2025, the Village Board approved the final design and park elements for the redevelopment of Doogan Park. This includes ten (10) lighted pickleball courts, adding lighting to the existing tennis courts, a restroom building with shaded gathering area, the redevelopment of the soccer field and baseball field, a playground, half basketball court, a looped trail, improvements/expansion of the north and south parking lots, landscape improvements, detention basin and all amenities in support of the redevelopment.
The final plan includes the removal of the bocce ball courts and sledding hill, the addition of a detention basin and adding light for the two existing tennis courts. The removal of the bocce ball courts and sledding hill are pending approval by the State related to the OSLAD grant.
In the course of design work, CBBEL performed work above the scope of the proposal that was necessary to develop the project in a manner that meets all code and regulatory requirements. These costs are detailed in the attached proposal Supplement #1 submitted by CBBEL and include tasks A, B, C and D
A. Design and engineering for the parking lot lighting
B. Stormwater Analysis
C. Detailed design for drainage improvements for the watershed
D. Design alternative cost estimates and coordinati...