Marley Creek Ponds - Quote Award
History
We have taken over the Marley Creek Ponds behind the townhomes in Marley Creek and Breckenridge (one of three). The ponds are in need of shoreline stabilization. This restoration of shoreline at Marley Creek Ponds will be done by Pizzo & Associates. They have done many projects within the village such as Collette Highlands. This is for one (1) pond only.
Cost for this project will be $32,221.38. We will also budget for the Stewardship Proposal (attached) in next year's budget.
Financial Impact
Budget adjustment to Account No. 283-4003-451-4350
Recommended Action/Motion
I move to approve waiving the bid process;
And
To approve accepting the quote from Pizzo & Associates for a cost not to exceed $32,221.38;
And
To approve a budget adjustment to Account No. 283-4003-451-4350 at a cost not to exceed $32,221.38;
And
To approve authorizing the Village Manager to execute the contract.