File #: 2022-0005    Version: 0 Name: Public Works Pond (#16-13) Shoreline Stewardship Renewal (2022 - 2024)
Type: MOTION Status: PASSED
File created: 12/20/2021 In control: Board of Trustees
On agenda: 1/4/2022 Final action: 1/4/2022
Title: Public Works Pond (#16-13) Shoreline Stewardship Renewal (2022 - 2024)
Attachments: 1. Proposal - Cardno, 2. Proposal - Davey, 3. Proposal - Pizzo, 4. Proposal - V3
Title
Public Works Pond (#16-13) Shoreline Stewardship Renewal (2022 - 2024)

History
In 2020, the Village issued a RFQ to expand the number of pre-qualified Ecological Restoration Contractors (ERCs) utilized for a variety of restoration projects. That RFQ resulted in an increase pf ERCs from two (2) to four (4). These ERCs (Cardno Inc., Davey Resource Group, Pizzo & Associates, and V3 Companies) represent the pool of contractors from which the Village solicits shoreline restoration and stewardship (i.e. maintenance) proposals.

A typical shoreline restoration project begins with one (1) year of establishment followed by three (3) to five (5) years of shoreline maintenance, otherwise known as a shoreline stewardship. After the initial shoreline stewardship period is completed, proposals for a continuation of maintenance, typically for three (3) to five (5) years, are requested from the pre-qualified ERCs.

Stewardship periods for several ponds are concluding at the end of 2021, including Public Works Pond (#16-13). As such, the Public Works Department requested proposals from all four (4) ERCs to continue the shoreline maintenance of this pond for three (3) years, with the option to extend the stewardship for an additional two (2) years.

The scope of work over the three (3) year stewardship includes the maintenance of existing native plantings, the control of invasive woody and herbaceous flora, one (1) prescribed burn, and supplemental seeding. The proposals represent the cost for three (3) years of shoreline maintenance from 2022 through 2024, plus an optional cost for (2) additional optional years of maintenance (2025 - 2026). A summary of the proposals for Public Works Pond can be found below:

5 Year Total Cost:

V3 Companies - $21,225.00
Cardno, Inc. - $24,700.00
Pizzo & Associates - $27,410.00
Davey Resource Group - $29,850.00


V3 Companies submitted the lowest proposal and is the recommended contractor for the continuation of shoreline stewardships a...

Click here for full text