Title
Civic Center Parking Lot Drainage Improvements Bid
History
Eight bids were received for the Civic Center Parking Lot Drainage Improvements on July 23, 2012. at 11:00 a.m. The low bid was from Stip Brothers Excavating, Inc at a cost of $13,990.00. The amount budgeted for this job was $33,000.00.
On August 6, 2012, this item was reviewed and approved by the Recreation & Parks Committee and referred to the Village Board for approval.
Financial Impact
The funds will come from the Civic Center account 021-1800-443500 - Grounds ($33,000.00 was budgeted).
Recommended Action/Motion
I move to accept the bid amount of $13,990.00 from Stip Brothers Excavating, Inc.