File #: 2014-0101    Version: Name: Centennial Park Aquatic Center Non-slip Flooring Bid
Type: MOTION Status: PASSED
File created: 2/10/2014 In control: Board of Trustees
On agenda: 4/7/2014 Final action: 4/7/2014
Title: Centennial Park Aquatic Center Non-slip Flooring Bid
Attachments: 1. Results, 2. Madison Coatings

Title

Centennial Park Aquatic Center Non-slip Flooring Bid

 

History

On February 5, 2014 at 11:00 a.m. bids were opened for non-slip flooring in the pump rooms and washrooms at Centennial Park Aquatic Center. Four (4) bids were submitted, and upon reviewing the bids, it was determined that the low bid was not responsible as the amount could not cover the cost of materials for the job. Staff contacted this bidder regarding his proposal. He indicated that he did not fully understand the scope of work and therefore requested to be disqualified. The next lowest qualified bidder was Madison Coatings Co. Inc. at $41,368. The budgeted cost was $31,000.00.

 

On March 17, 2014 this item was reviewed by the Parks & Recreation Committee, recommended for approval, and referred to the Village Board of Trustees for consideration.

 

Financial Impact

The funds will come from the Pool Buildings line item 283-4005-443100, $31,000 budgeted. There is $10,000 budgeted for shower tower replacement in the Pool line item 283-4005-443150 which we will not be purchasing this year.

 

Recommended Action/Motion

I move to approve the CPAC non-slip flooring bid from Madison Coatings Co. Inc. at a cost not to exceed $41,368.