Schussler Park V3 Construction Group Change Order and Contract Amendment

History
The Village awarded RFP #23-037 to V3 Construction Group on May 15,2023 as the general contractor for the redevelopment of Schussler Park. On April 15,2024, the Board approved the expenditure of $319,056.83 for the purchase of a restroom/storage building from Romtec Building & Pumping Systems through the Sourcewell Joint Purchasing Cooperative Contract #081721-RMT, as well as a contract for installation of that building in a not-to-exceed amount of $350,000.00

The Village purchased the restroom/storage building directly from Romtec Building & Pumping Systems through Sourcewell Contract #081721-RMT. This direct purchase resulted in a savings of $16,262.98. The Board approved this purchase (File # 2024-0300) at a cost not to exceed $319,056.83. A subsequent change order (attached) was executed on June 3, 2024 in the amount of $5,407.06 for additional features to the facility bringing the total purchase to $324,463.89. Installation was not included in these costs.

On May 20, 2024, the Board approved FY 2023 Budget Amendment No. 1, which provided an adjustment from the initially approved $350,000 allocated to the bathroom/storage building installation to a $500,000 total budgeted amount. A contract was not executed at the time of the initial $350,000.00 approval nor at the time of the Budget Amendment as staff awaited a firm quote.

V3 has provided a quote (attached), for the installation of the restroom/storage building, to be done as an adjustment to the scope and cost of the initial contract awarded on May 15, 2023, with the installation of the restroom/storage building totaling $648,653.00. Explanations for costs above what was initially expected include:

· All work will be performed by union labor at union wages.

· Utilities
o Exterior plumbing connection not identified on early plan set.
o Exterior plumbing includes watermain quality pipe due to sanitary and stor...