Background.  The Spring Creek Agreement obligates Gallagher & Henry to turn over Doctor Marsh to the Forest Preserve District of Cook County.  Cook County has still not taken this property so the Village can hold it until the County accepts it.  This property includes Doctor Marsh and Spring Creek, both of which need restoration.  The Army Corps of Engineer has agreed to this area being designated a wetland mitigation bank.   This allows mitigation dollars from developers and projects to be funneled into this site for restoration, keeping the funds in Orland Park and reimbursing the Village for its costs.

 

Currently, the Village is involved with two projects that require wetland mitigation.  One is 156th Street between LaGrange Road and Ravinia Avenue.  The other is the bikepath along the ComEd easement near 139th Street. 

 

Proposal.  A suitable site and a restoration plan for that site are required.  The Doctor property is a suitable site and Christopher Burke has prepared a scope of work not to exceed $56,600.  The scope of work specifically addresses the 156th Street project but included identification of other potential restoration on the site.  The idea is that this will draw other mitigation funds required by the Army Corps and the Village can get reimbursed.    The scope of work includes topographical survey, wetland field reconnaissance, assessment report, conceptual wetland mitigation plan, agency coordination and final engineering plans for a wetland mitigation/restoration project on the Doctor property.

Financial Impact

Budget adjustment of $56,600 from the General Fund fund balance to Account #101-203-416-3280.

Recommended Action/Motion

I move to approve a budget adjustment in the amount of $56,600.

 

And

 

I move to approve the proposed scope of work by Christopher Burke Engineering Ltd. in an amount not to exceed $56,600.