Title/Name/Summary
Stellwagen Farmhouse Foundation Restoration Bid #15-019 Rejection
History
QUICKFACTS
Project
Stellwagen Farmhouse Foundation Restoration Bid #15-019 Rejection
Petitioner
Development Services Department
Purpose
To reject the bid response to Bid #15-019; Stellwagen Farmhouse foundation restoration.
OVERVIEW AND BACKGROUND
On July 14, 2015, the Village of Orland Park issued Bid #15-019 to solicit responses and proposals from contractors to correct and historically restore the Stellwagen Farm farmhouse building foundation.
On July 31, 2015, the Village received one response to the invitation to bid. The bid response from Molter Corporation was deemed not responsive to the bid criteria. Molter Corporation bid $41,555 to complete the work.
All non-responsive bids are rejected by the Village.
The Molter Corporation bid is attached for further review. Included in the attachments is a bid responsiveness analysis, describing what made the bid non-responsive, and a bid summary.
DEVELOPMENT SERVICES AND PLANNING COMMITTEE MOTION
On August 17, 2015, the Development Services Planning and Engineering Committee moved 3-0 to recommend to the Village Board of Trustees to reject the Molter Corporation response to Bid 15-019 as non-responsive to Village criteria.
This case is now before the Village Board of Trustees for consideration.
Recommended Action/Motion
I move to reject the Molter Corporation response to Bid #15-019 as non-responsive to Village criteria.