131st Street Lift Station Motor #2 Repair - Board Approval
History
Pump #2 at the 131st Street Lift Station experienced a failure necessitating its shutdown. The 60 hp motor and pump assembly were removed and sent to Gasvoda & Associates, Inc., of Calumet City, Illinois (the authorized manufacturer’s representative), for evaluation. They determined that there was a motor winding failure requiring the motor to be rewound. In addition, the shaft required metalizing along with bearing and seal replacement. The cost for this work totaled $5,230. The pump was reinstalled on January 7, 2008, and is in good operating order.
On January 14, 2008, this item was reviewed and approved by the Public Works and Engineering Committee and referred to the Board for approval.
INFORMATION PREVIOUSLY PROVIDED AS PART OF THE JANUARY 14, 2008, PUBLIC WORKS AND ENGINEERING COMMITTEE PACKET.
Financial Impact
This is a non-budgeted emergency repair. There is a Board approved Contingency Fund (Account #031-6001-433.84-95) totaling $100,000 for this type of work. Funds in the amount of $5,230 will need to be transferred from this account to the Machinery and Equipment Account #031-6003-433.43-20.
Recommended Action/Motion
I move to approve the transfer of $5,230 from the Contingency Account to the Machinery and Equipment Parts Account;
and
Approve payment to Gasvoda & Associates, Inc., of Calumet City, Illinois, for the repair of Pump #2 at the 131st Street Lift Station in an amount not to exceed $5,230.