Title
Sportsplex Gymnasium Flooring Change Order
History
Upon removal of the existing gym flooring it was discovered that the concrete floor is not level in the northeast corner of the building. We have received an estimate from Floors Incorporated, the contractor currently reconstructing the floor, in the amount of $4700 to perform the work to correct this.
On September 6, 2011, this item was reviewed and approved by the Parks, Recreation, and Environmental Initiatives Committee and referred to the Board for approval.
Financial Impact
The funds will come from the remaining balance originally allocated to this project in account 283-4007-451.7010. There is $14,100 remaining.
Recommended Action/Motion
I move to approve a change order to Floors Incorporated $4,700.00 for the leveling of the gymnasium concrete sub-floor.