File #: 2025-0147    Version: 0 Name: 143rd Street and John Humphrey Drive Intersection and Bridge Improvements, Phase III Construction Engineering/Observation Services, Contract Award Recommendation
Type: MOTION Status: PASSED
File created: 2/12/2025 In control: Board of Trustees
On agenda: 2/17/2025 Final action: 2/17/2025
Title: /Name/Summary 143rd Street and John Humphrey Drive Intersection and Bridge Improvements, Phase III Construction Engineering/Observation Services, Contract Award Recommendation
Attachments: 1. Staff Availability Letter, 2. Phase III Scope of Services, 3. Professional Fees and Manhours, IDOT Forms
Title/Name/Summary
143rd Street and John Humphrey Drive Intersection and Bridge Improvements, Phase III Construction Engineering/Observation Services, Contract Award Recommendation

History
The Engineering Department issued a Request for Qualifications (RFQ #24-057) for Phase III Construction Engineering/Observation Services for the 143rd Street and John Humphrey Drive Intersection and Bridge Improvements project. The project received federal construction funding of $3 million through the Surface Transportation Program (STP). The funding applications were managed and processed by the Southwest Conference of Mayors (SCM), Chicago Metropolitan Agency for Planning (CMAP) and Illinois Department of Transportation (IDOT). Since the project received federal funding, it required a Quality Based Selection (QBS) process with cost negotiation only after the initial selection was made. The RFQ was issued through the Village's BidNet system and the following six (6) engineering consultants submitted their responses:

1. Baxter & Woodman, Inc.
2. Benesch
3. EXP
4. Patrick Engineering Inc. (dba RINA)
5. Thomas Engineering Group, LLC
6. TranSystems Corporation

The Selection Committee ranked the RFQ responses based on the following selection criteria defined in the RFQ:

- Firm's Phase III experience with intersection improvements, traffic signal upgrades, drainage improvements, and dry land improvements using pile supported embankment system - 20%
- Project team’s experience with similar projects - 25%
- Project team that will work on the project - 35%
- Overall completeness of submittal and project understanding - 10%
- Selection team’s discretion - 10%
Total - 100%

After reviewing the qualifications, staff invited the top three firms for in-person interviews at the Village Hall. Based on the outcomes of the interviews, the Selection Committee ranked and scored each consultant as follows:

1. Patrick Engineering Inc. (dba RINA) 91
2. EXP 89