File #: 2009-0011    Version: Name: 104th Avenue - (159th Street to 167th Street Improvements) Phase II - Part B Engineering Supplement - Board Approval
Type: MOTION Status: PASSED
File created: 1/7/2009 In control: Board of Trustees
On agenda: 1/19/2009 Final action: 1/19/2009
Title: 104th Avenue - (159th Street to 167th Street Improvements) Phase II - Part B Engineering Supplement - Board Approval

Title

104th Avenue - (159th Street to 167th Street Improvements)

Phase II - Part B Engineering Supplement - Board Approval

History

On October 1, 2007, the Board of Trustees approved entering into an agreement with the Cook County Highway Department for Phase I and Phase II engineering for improvements to 104th Avenue from 159th Street to 167th Street.  This supplemental agreement is for additional design engineering that is required for Part B final design and geotechnical engineering plans for the timber pile platform in poor soil that was requested by Cook County Highway Department.  The total cost of the supplement involving the Village is $61,195 of which the Village is responsible for $15,299 or 25%.

 

On January 12, 2009, this item was reviewed and approved by the Public Works and Engineering Committee and referred to the Board for approval.

 

Financial Impact

There are sufficient funds in Line Item 054-0000-499.32-50 for this expenditure.

 

Recommended Action/Motion

I move to approve the supplemental agreement with the Cook County Highway Department for additional design engineering for street improvements of 104th Avenue (159th Street to 167th Street) for an amount not to exceed $15,299;

 

And

 

Approve authorizing the Mayor and Village Clerk to execute said Agreement.