Com Ed Proposal to Lift
History
The concrete foundation supporting the Com Ed transformer that serves the John Humphrey complex needs to be repaired and the transformer reset by the utility company. It is the responsibility of the owner (the Village) to repair the concrete foundation base and this work can be accomplished by the Parks/Building Maintenance staff. Com Ed has provided a quote for the cost to reset the transformer following the in-house repair in the attached Customer Work Agreement. The cost is $5,625.57.
On March 17, 2014 this item was reviewed by the Parks & Recreation Committee, recommended for approval, and referred to the Village Board of Trustees for consideration.
Financial Impact
Funds are available in the Building Maintenance - Buildings account 010-1700-4701000.
Recommended Action/Motion
I move to approve accepting the ComEd quote for the lifting and setting of the transformer at the John Humphrey Complex in the amount of $5,625.57.