File #: 2018-0583    Version: Name: Solar Panel Installation – 10921 Sheridans Trail – Diaz Residence, Installation of 7.8 kW Solar Array as part of an Environmental Clean Technology (ECT) Review
Type: MOTION Status: PASSED
File created: 8/20/2018 In control: Board of Trustees
On agenda: 11/5/2018 Final action: 11/5/2018
Title: /Name/Summary Solar Panel Installation - 10921 Sheridans Trail - Diaz Residence, Installation of 7.8 kW Solar Array as part of an Environmental Clean Technology (ECT) Review
Attachments: 1. Aerial - 10921 Sheridans Trail, 2. Design Packet, 3. Solar Glare Report
Title/Name/Summary
Solar Panel Installation - 10921 Sheridans Trail - Diaz Residence, Installation of 7.8 kW Solar Array as part of an Environmental Clean Technology (ECT) Review

History
QUICKFACTS

Project
Solar Panel Installation - 10921 Sheridans Trail - Diaz Residence, Installation of 7.8 kW Solar Array as part of an Environmental Clean Technology (ECT) Review
2018-0583 / AR-18-00546

Petitioner
Eric Peterman, GRNE Solar

Purpose
The purpose of this petition is to install and maintain a roof-mounted solar panel system at a single-family residence located at 10921 Sheridans Trail.

Requested Actions: Appearance Review (Environmental Clean Technology)

Project Attributes
Address: 10921 Sheridans Trail
P.I.N.(s): 27-29-118-002-0000

Parcel Size: 0.27 acres
Building Size: 4,000 square feet

Comprehensive Plan Planning District: Grasslands Planning District
Comprehensive Land Designation: Single Family Residential
Existing Zoning: R-3 Residential District
Existing Land Use: Single Family Home

Surrounding Land Use:
North: R-3 Residential District - Single Family Home
South: LSPD Large Scale Planned Development District - Single Family Home
East: R-3 Residential District - Single Family Home
West: R-3 Residential District - Single Family Home

Preliminary Engineering: A structural engineer report was submitted with this petition, which concluded that the roof structure can safely support the weight of the proposed solar panels.

PLANNING OVERVIEW AND BACKGROUND
Section 6-314.C of the Land Development Code requires that the petitioner seeking a renewable energy or environmental clean technology system first obtain an Environmental Clean Technology (ECT) review from the Plan Commission. Subsequent to such a review, this project will follow the standard development review process. A review will next take place at the Development Services, Planning and Engineering Committee and then a final review and decision from the Village Board of Trustees.

PROJECT DES...