File #: 2016-0495    Version: 0 Name: Orlan Brook Drive Culvert Replacement - Bid and Construction Engineering Services
Type: MOTION Status: PASSED
File created: 6/29/2016 In control: Board of Trustees
On agenda: 7/5/2016 Final action: 7/5/2016
Title: Orlan Brook Drive Culvert Replacement - Bid and Construction Engineering Services
Attachments: 1. Baxter & Woodman Proposal, 2. Bid Tabulation, 3. Hasse Bid, 4. Baxter & Woodman - Signed Contract - Exhibit B - Orlan Brook Dr Construction Services, 5. Hasse Construction - Signed Contract - Orlan Brook Dr Culvert Replacement
Title
Orlan Brook Drive Culvert Replacement - Bid and Construction Engineering Services

History
Orlan Brook Drive was originally constructed in the early 1970’s. The culvert section of the construction involved the installation of two 72-inch corrugated metal culvert pipes that connected the two ponds south of Wheeler Drive. Over the past 40 years, these pipes have deteriorated considerably. There is significant deflection through the barrels of the pipes and the roadway pavement structure above the pipes has developed sink holes requiring significant patching over the past few years. The culvert pipes need to be replaced in order to maintain a structurally sound roadway.

On July 20, 2015, the Village Board approved a proposal from Baxter & Woodman to perform Phase I and Phase II Consulting Engineering Services for the Orlan Brook Drive Culvert Replacement Project. In order to facilitate the construction of the project, staff requested and received a proposal for Phase lll Construction Services from Baxter & Woodman. Also responsible for providing oversight for the efficient implementation of the 2016 Road Improvement Program, Baxter & Woodman has established themselves as a proficient and professional consultant to the Village. Therefore, staff recommends approving the proposal from Baxter & Woodman for Phase II Construction Services for the Orlan Brook Drive Culvert Replacement Project in an amount not to exceed $32,712 (proposal attached), plus a $5,000 contingency for a total of $37,712.00.

An Invitation to Bid for the culvert replacement work was advertised in the Southtown Star Newspaper on May 31, 2016. Sealed bids were opened by the Village Clerk’s office on June 17, 2016 (summary attached). Eight (8) sealed bids were received. Bids were submitted by Airy's Inc. of Tinley Park, Illinois; D. Construction of Coal City, Illinois; Hasse Construction Company, Inc. of Calumet City, Illinois; Kovilic Construction Company, Inc. of Franklin Park, Illin...