header-left
File #: 2011-0355    Version: Name: 2011 Road Improvement Program - Bid Award
Type: MOTION Status: PASSED
File created: 6/1/2011 In control: Board of Trustees
On agenda: 6/20/2011 Final action: 6/20/2011
Title: 2011 Road Improvement Program - Bid Award
Attachments: 1. 2011 ROAD IMPROVEMENT PROGRAM BID TAB SHEET, 2. 2011 ROAD IMPROVEMENT PROGRAM BID SUMMARY SHEET, 3. Signed Contract.pdf
Title
2011 Road Improvement Program - Bid Award
History
The annual Road Improvement Program has a Board approved line item in the amount of $2,720,000 in the Fiscal Year 2011 Budget.

Historically, the project consists of milling the existing asphalt surface to remove failed pavement and overlay milled pavement surface with a new wear-surface. Streets in various subdivisions throughout the Village have been selected for resurfacing by Staff based upon condition analysis. The list of selected streets has previously been presented to the Committee for review and comment. In addition to pavement-related work, failed curbs are replaced or repaired on an as-needed basis and hazardous sidewalks are replaced. As an additional part of the Road Improvement Program, storm sewer underdrains will be installed in various locations within areas where excessive groundwater has or may cause premature pavement failure. This project also includes significant patching throughout the Village to prolong the service life of adjacent pavement sections.

A Request for Bids was advertised in the SouthtownStar Newspaper on Friday, May 13, 2011. Six companies submitted a sealed bid proposal. Bid proposals were received from: Alpha Construction Co. of Hazel Crest, Illinois; Central Blacktop Co. Inc. of LaGrange, Illinois; Crowley-Sheppard Asphalt, Inc. of Chicago Ridge, Illinois; James D. Fiala Paving of Bolingbrook, Illinois; K-Five Construction Corp. of Lemont, Illinois; and P.T. Ferro Construction Company of Joliet, Illinois. The sealed bids were publicly opened and read aloud by the Clerk’s Office at 11:00 a.m. on Friday, May 27, 2011.

Following a full bid review, Crowley-Sheppard Asphalt, Inc. has been deemed to be the low qualified bidder, providing a bid in the amount of $1,892,530.50 which is below the engineer’s estimate and below the Board approved budgeted amount for the anticipated 2011 Program (Bid Summary Sheet attached). Of the $2,720,000 budgeted, $263,400 w...