File #: 2008-0574    Version: Name: Streetlight Relocation at 156th Street and LaGrange Road - Board Approval of Proposal/Contract
Type: MOTION Status: PASSED
File created: 9/3/2008 In control: Board of Trustees
On agenda: 9/15/2008 Final action: 9/15/2008
Title: Streetlight Relocation at 156th Street and LaGrange Road - Board Approval of Proposal/Contract
Attachments: 1. Home Towne Electric

Title

Streetlight Relocation at 156th Street and LaGrange Road - Board Approval of Proposal/Contract

History

As part of the 156th Street extension between LaGrange Road and Ravinia Avenue, some incidental work on the streetlights needs to be performed on both the east and west sides of LaGrange Road.  Lowe’s will be responsible for the temporary streetlights on the east side of LaGrange Road as part of their development.  The two poles on the west side of LaGrange Road will need to be relocated by the Village to allow for the new road extension to Ravinia Avenue.

 

Staff has contacted the electrical contractor (Home Towne Electric, Inc. of Lake Villa, Illinois) who will be doing the work for Lowe’s and who is currently working on the 159th Street and LaGrange Road project.  To lessen the costs of mobilization, staff has requested a cost from Home Towne Electric to relocate the two poles that are the responsibility of the Village.  Home Towne Electric, Inc. has submitted a proposal with itemized costs totaling $11,755 for the relocation work.

 

On September 8, 2008, this item was reviewed and approved by the Public Works and Engineering Committee and referred to the Board for approval.

 

Financial Impact

The 2007/2008 Fiscal Year Capital Improvement Budget has a Board approved line item (054-0000-499.71-25) for the 156th Street Road Extension Project to cover the costs of this work.

Recommended Action/Motion

I move to approve accepting the proposal from Home Towne Electric, Inc. of Lake Villa, Illinois, for the relocation of two streetlight poles on the west side of LaGrange Road at 156th Street for a cost not to exceed $11,755;

 

And

 

Approve authorizing the Village Manager to execute the proposal/contract.