File #: 2017-0161    Version: 0 Name: Downtown Main Street Parking Deck - Final Contract Amount
Type: MOTION Status: PASSED
File created: 3/2/2017 In control: Board of Trustees
On agenda: 3/6/2017 Final action: 3/6/2017
Title: Downtown Main Street Parking Deck - Final Contract Amount

Title

Downtown Main Street Parking Deck - Final Contract Amount

 

History

On February 20, 2017, the Village approved a collection of change orders over $10,000 related to the Downtown Main Street Parking Deck. 

 

At this time, Staff is seeking formal approval to amend the current contract to reflect a total contract amount of $15,252,445.00, which matches the amount presented in the staff report prepared for the Board meeting held on February 20, 2017 (2017-0065).

 

This adjustment is inclusive of all change orders over the life of this project, and represents the final project cost.

 

Recommended Action/Motion

I move to approve a final contract amount for the Downtown Main Street Parking Deck with Walsh Construction Company II, LLC for $15,252,445.00 and authorize the Interim Village Manager to execute any related change orders on behalf of the Village.