header-left
File #: 2012-0385    Version: 0 Name: 143rd Street Watermain Completion Agreement
Type: MOTION Status: PASSED
File created: 6/13/2012 In control: Board of Trustees
On agenda: 6/17/2012 Final action: 6/18/2012
Title: 143rd Street Watermain Completion Agreement
Attachments: 1. Settlement Agreement and Release Brothers V3 VOP

Title

143rd Street Watermain Completion Agreement

 

History

A portion of the watermain that was constructed on 143rd Street between Ravinia Avenue and Main Street is being relocated to complete the project in accordance with the design specifications.  Design and construction oversight is being provided by V3 Companies and the work is being performed by Brothers Asphalt.  Both companies will share in the cost of relocation.  Attached is a completion agreement outlining the requirements of all parties.

 

Financial Impact

None

 

Recommended Action/Motion

 

I move to approve the agreement with V3 Companies of Illinois, Ltd. and Brothers Asphalt and Paving, Inc. to complete the 143rd Street Watermain project.