Title
Clock Tower Brick Repair Bid Award
History
Five bids were received on May 24, 2011 at 11:00 AM for the Clock Tower Brick Repair work for the Village Hall. The low bid was from Berglund Construction Company of Chicago at a cost of $198,523.00. Budgeted for this project was $200,000.00. Engineering fees were charged to this account at $4,500.00, leaving a balance of $195.500.00. There are funds in the account for overage, (savings on HVAC). It is not anticipated that either alternate will be performed by the contractor.
On July 5, 2011 this item was reviewed and approved by the Parks, Recreation, and Environmental Initiatives Committee and referred to the Board for approval
Financial Impact
The funds will be come from the Building Maintenance account 010-2100-424.4310, $200,000.00 budgeted.
Recommended Action/Motion
I move to approve accepting the low bid from Berglund Construction for the amount of $198,523.00.
And
Authorize the Village Manager to execute the contract.