File #: 2012-0711    Version: 0 Name: Fox’s Restaurant Storm Sewer Connection Project - Change Order
Type: MOTION Status: PASSED
File created: 11/28/2012 In control: Board of Trustees
On agenda: 12/3/2012 Final action: 12/3/2012
Title: Fox’s Restaurant Storm Sewer Connection Project - Change Order

Title

Fox’s Restaurant Storm Sewer Connection Project - Change Order

History

On September 4, 2012, the Board approved awarding the bid for the installation of a new storm sewer at the Fox’s Restaurant at 143rd Street and Ravinia Avenue to Swallow Construction, Inc. of Downers Grove, Illinois, for a cost not to exceed $114,500.00.  The project was completed over the course of one week during the month of October.  During construction, a change in plan was required due to unexpected piping configurations which were found.  The unexpected configuration on the old storm sewer required the contractor to re-lay several lengths of previously installed pipe.  After discussion with the contractor, a change order in the amount of $5,688.62 is being requested.

 

Financial Impact

There are sufficient funds available in account 054-0000-484800 to cover the cost of this extra work.

 

Recommended Action/Motion

I move to approve reimbursing Swallow Construction, Inc. of Downers Grove, Illinois, for the change order during construction of the Fox’s Storm Sewer Project in an amount not to exceed $5,688.62.