File #: 2015-0282    Version: 0 Name: Main Pump Station Emergency Generator Breaker (Emergency Replacement) - Proposal
Type: MOTION Status: PASSED
File created: 4/29/2015 In control: Board of Trustees
On agenda: 5/4/2015 Final action: 5/4/2015
Title: Main Pump Station Emergency Generator Breaker (Emergency Replacement) - Proposal
Attachments: 1. ESI Proposal

Title

Main Pump Station Emergency Generator Breaker (Emergency Replacement) - Proposal

 

History

Public Works staff experienced a failure of the back-up emergency generator breaker that is responsible to provide emergency power to the Village’s Main Pump Station. In order to repair this critical component associated with the consistent and timely delivery of water, staff contacted Electrical Systems, Inc. (ESI), East Hazel Crest, Illinois. ESI’s costs include $6,730 for parts and $3,390 for labor; for a total of $10,120.00.

 

ESI has experience in repairing water-system electrical components and have assisted with emergency repairs in the past.  Due to the importance of the backup generator, and the time it takes to order and receive parts, ESI was contacted so that the parts could be ordered in conjunction with the Committee and Village Board approval process.

 

Due to various failures of related equipment, Greely and Hansen LLC, Chicago, IL was requested to evaluate the motor control center and its ability to effectively switch from ComEd power to generator power.  Based on Greely and Hansen’s recommendations, Public Works will be returning to the Committee and Board for approval to upgrade the system.

 

On May 4, 2015, this item was reviewed and approved by the Public Works Committee and referred to the Village Board for approval.

 

Financial Impact

Funds are available in the contingency account, 031-6001-484950, and will be transferred to accounts 031-6002-461700 and 031-6002-443200 to cover the cost for this emergency repair. 

 

Recommended Action/Motion

I move to approve to waive the bid process;

 

And

 

Transfering funds from the water fund contingency account to the appropriate operating accounts;

 

And

 

Accept the proposal from Electrical Systems, Inc. (ESI) of East Hazel Crest, Illinois for the emergency replacement of the Main Pump Station Emergency Generator Breaker at a cost not to exceed $10,120.00.