Title
Pool Painting Change Order
History
Madison Construction (low bidder) is currently painting the pool. They have submitted a quote to paint the following two additional areas: under the stairs (white), and striping of the large tube slide (green), both are still within the budgeted amount. Cost for the striping is $4,990.00, and bridge and step resurfacing color change is $6,010.00. Because of the impending pool opening it is noted that we need to move forward on this item in order to assure completion in a timely manner.
Financial Impact
The funds will come from the Pool account 283-4005-443150. $409,000.00 was budgeted and $395,000.00 was the bid approved by the Board, leaving $14,000.00.
Recommended Action/Motion
I move to approve accepting change orders for Madison Construction not to exceed $11,000.00.