File #: 2019-0158    Version: 0 Name: Village Hall Complex Improvements - Bid Award
Type: MOTION Status: PASSED
File created: 2/25/2019 In control: Board of Trustees
On agenda: 3/18/2019 Final action: 3/18/2019
Title: /Name/Summary Village Hall Complex Improvements - Bid Award
Attachments: 1. Bid Tab, 2. Signed Contract, 3. Strand Associates Proposal, 4. Change Order 5 - signed
Title/Name/Summary
Village Hall Complex Improvements - Bid Award

History
The Orland Park Village Hall Complex includes the Fredrick T. Owens Village Hall, William R. Vogel Civic Center, Franklin E. Loebe Recreation Center and the Ara Pace Veteran's Memorial. As a part of a larger project, a scope of work was developed to initiate improvements to the parking lots, pedestrian circulation, lighting, security and landscaping for the Village Center. This is Phase II of the Village Hall Complex improvements, with Phase I being the roundabout at 147th Street and Ravinia Avenue. The cross departmental effort includes Development Services, Public Works and Parks & Grounds coordinating planned improvements and budgeting to have one project efficiently and cost effectively address the needs of the Village Hall Complex.

Similar to the roundabout project, it is important for this work to be completed prior to the Taste of Orland in August. As such, this item is bypassing Development Services Committee and going straight to the Village Board for consideration. This will allow the project to commence sooner to stay within proposed timelines.

A request for bids was advertised on February 11, 2019, nine vendors were notified through BidNet. Thirty-one companies downloaded the specifications. The bid opening for the Village Hall Complex Improvements was conducted on February 26, 2019, at 11:00 a.m. Austin Tyler Construction, LLC. of Elwood, Illinois was the lowest responsive qualified bidder with a bid of $1,550,735 for the base bid and alternate items 1, 2, 3, 4 and 7. Attached is a summary of the bid totals for the contractors. In addition to the base bid work, staff is proposing to include the following alternate bid options in the contract:

- Alternate 1 - John Humphrey Complex Parking Lighting
- Alternate 2 - Two additional landscape columns in roundabout
- Alternate 3 - Additional lighting bollards for west sidewalk to Village Hall
- Alternate 4 - Collapsible bollar...