Facility Door Replacements - Village Hall and Utility Sites

History
Guided by the 2022 "Facilities Condition Assessment", the Public Works Department has been working to replace damaged doors and inoperable ADA controls throughout the Village. As such, Public Works requested a proposal from Midwest Mechanical Group, Inc. (“Midwest Mechanical”), who participate in the Omnia Cooperative program (Contract # 159053), to complete door replacements at several Water Utility Sites and Village Hall this year. It should be noted that Public Works received individual quotes for many of these same doors from other vendors, and pricing came in on average 10% higher than the proposals received by Midwest Mechanical.

Based on funding for door replacements in 2025, eight (8) doors at Village Hall and seven (7) doors at Water Utility sites were selected for replacement, for a total of fifteen (15) door replacements. Funding for additional door replacements will be requested for 2026.

The scope of work includes the removal and replacement of existing doors, door frames, door hardware, and ADA controls where applicable. The proposals submitted by Midwest Mechanical are based on pricing from Omnia Contract # 159053. Pictures showing the location of the door replacement areas are included in the project proposals, which are attached for reference.

A summary of the proposal submitted by Midwest Mechanical, which are based on Omnia Partners Contract # 159053, is provided below:

Facility Door Replacements
Village Hall (8 Doors): $67,020.00
Utility Sites (7 Doors) $65,093.00
Total: $132,113.00

Based on price and company qualifications, staff recommends approving proposal from Midwest Mechanical Group, Inc., participating in the Omnia joint purchasing program, for $132,113.00. A 10% contingency of $13,211.30 is requested to address change orders made necessary by circumstances not reasonably foreseeable at the time the proposals are signed, for a total contract price not to...