Schussler Park Phase II - 14609 Poplar Road - Appearance Review for all-inclusive playground, 1/2 basketball court, 24'x48' pavilion, and landscape improvements
History
This case is the Phase II improvements related from Phase I of Schussler Park Renovations (Case No. 2022-0921). The phase two improvements includes the installation of an all-inclusive playground, 1/2 basketball court, 24'x48' pavilion, and landscape improvements.
All-Inclusive Playground Equipment
Playground equipment is permitted so long as it is located at least 5 feet from the lot lines and does not obstruct storm water flow. Both requirements have been met with this proposed plan. Playground equipment specifications will be reviewed by the building division through the permit process prior to installation.
Landscape Plan
The proposed additional plantings comply with the intent of Section 6-305 of the Land Development Code by providing a mix of native shade trees, ornamentals, shrubs, and prairie species that support ecological function, seasonal interest, and long-term landscape sustainability. No prohibited species are included, and the plant schedule maintains compliance with required diversity, native percentage, and evergreen/deciduous ratios. The overall landscape plan for Schussler Park was reviewed and approved during Phase I, and these additions are consistent with that approval while going above and beyond code requirements.
Basketball Court
The proposed improvements include installation of a half basketball court. In accordance with Section 6-302.C.41, sport courts are permitted within rear setbacks provided they are set back at least 5 feet from the lot line in all districts. The proposed court does not include fencing and is located away from all lot lines.
Pavilion
The proposed improvements include construction of a 24’ by 48’ pavilion. The pavilion consists of a steel post-and-beam frame with a pitched roof supported by evenly spaced columns. Each column base will ...