Title: /Name/Summary AT&T - 8741 166th Place - Installation of New Equipment
Attachments: 1. MRCHI030564_REV K_10.24.2024.APPROVED, 2. L1.103024, 3. ATT-8741 166th place Application
Date Ver.Action ByActionResultAction DetailsMeeting Details/Media Packet
No records to display.

Title/Name/Summary

AT&T - 8741 166th Place - Installation of New Equipment

 

History

QUICKFACTS

 

Project

AT&T - 8741 166th Place - Appearance Review

Legistar Case 2024-0419

AR-24-00438

 

Petitioner                      

Anthony Barajas, Mastec

1351 Irving Park Road, Itasca, IL 60143

 

Purpose

The purpose of this petition is to replace an existing Village owned light pole and lamp head, with new pole and lamp head, in order to install new equipment on the light pole.

 

Requested Actions: Appearance Review

 

Project Attributes

Address: 8741 166th Place, Orland Park

 

P.I.N.(s): N/A

 

Parcel Size: N/A

 

Comprehensive Plan Planning District: Fernway

Comprehensive Land Designation: Single Family Residential

Existing Zoning: Residential

Existing Land Use: Right of way

 

Surrounding Land Use:

North: R-2A -Single Family Residential

South: R-2A -Single Family Residential

East: R-2A -Single Family Residential

West: Unincorporated - Single Family Residential

 

 

PROJECT DESCRIPTION & CONTEXT

 

The petitioner intends to replace existing aluminum light pole and light fixture with new pole and light fixture, in order to install a new antenna, RRUS, power distribution panel, fiber demarcation box etc. on the new light pole. The existing concrete foundation will be replaced to accommodate new pole, new meter, and new cables and ground.

 

The existing signs on the existing pole, including Street Names, “No Parking”, and “Curb your Dog” signs will be removed from existing pole and re-installed on the new pole.

 

During construction, a temporary lighting structure will be installed in conformance with the Village’s temporary lighting standards, and lighting will be provided from dusk to dawn.

 

 

PLANNING OVERVIEW

The petitioner is proposing performing the scope of work:

•                     Replace existing aluminum light pole with new aluminum light pole and light fixture

•                     Install (1) New Amphenol Omni Antenna

•                     Install (1) RRUS - 8843

•                     Install (1) RRUS - 4449

•                     Install (1) New Power Distribution Panel

•                     Install (1) New Fiber Demarcation Box

•                     Install (4) Ericsson AC-08 PSU, (2) per RRU

•                     Install new meter trough

•                     Install cabling as required

•                     Install ground as required

•                     Replace concrete foundation

 

 

ENGINEERING:

Christopher B. Burke Engineering Ltd. has reviewed and approved the engineering plans and structural analysis for the AT&T Mobility - 8741 166th Place project, based on their review of the following documents:

•                     Engineering Plans prepared by Fullerton Engineering bearing a revision date of October 24, 2024

•                     CBBEL Review Letter dated October 12, 2024, annotated with responses from project engineer

•                     Structural Analysis Report by Fullerton Engineering bearing a revision date of April 19, 2024, PREVIOUSLY SUBMITTED

•                     Orland Park Small Wireless Facilities Appearance Review and ROW Permit Application dated May 10, 2024, PREVIOUSLY SUBMITTED

 

 

Recommended Action/Motion
The Appearance Review for AT&T Mobility - 8741 166
th Place, case number 2024-0419, as depicted on list of documents listed above has been administratively approved on October 30, 2024, subject to the following conditions:

 

1.                     The project will be in substantial conformance with the project documents listed above;

2.                     All Building permit requirements are met, and fees are paid at time of permit pick up;

3.                     Payment of the engineering review fees shall be paid in full at time of permit pick up;

4.                     Pass all inspections by Orland Park Public Works and Engineering Departments