File #: 2020-0456    Version: 0 Name: John Humphrey Complex Renovations (Design-Build) - Phase II Change Order
Type: MOTION Status: PASSED
File created: 6/29/2020 In control: Board of Trustees
On agenda: 7/6/2020 Final action: 7/6/2020
Title: John Humphrey Complex Renovations (Design-Build) - Phase II Change Order
Attachments: 1. JHC Renovations (Design Build) - Phase II Change Order, 2. Contract - Signed

Title

John Humphrey Complex Renovations (Design-Build) - Phase II Change Order

 

History

The Village of Orland Park awarded V3 Construction Group, LTD. the contract in accordance with their proposal submitted March 24, 2020, for Design-Build John Humphry Complex Renovations phase II to renovate the concession stand and restrooms for a Guaranteed Maximum Price of four hundred forty-eight thousand three hundred and no/100 ($448,300.00) dollars.

 

The Scope of Work includes:

•                     Removal and replacement of existing roof;

•                     Renovation of the women's restroom to meet generally accepted industry standards;

•                     Renovation and expansion of the men's restroom, the number of stalls and sinks to meet generally accepted industry standards;

•                     Renovation and conversion of the concession stand area to be an exterior service only stand.

 

V3 has submitted a change order (attached) for the following items:

•                     Change from quarry tile floor to non-slip epoxy flooring to storage room and entry vestibule (185sf): $2,220

•                     Mop sink and laundry tub in storage space (code requirement): $3,500

•                     Battery operated faucets (2 per restroom): $2,600

•                     Replacement urinals (3): $2,040

•                     Electrical upgrades required to achieve the scope of the project: $8,250

Total of Change Order: $12,610

 

Staff seeks Board approval for these changes.

•                     The mop sink and laundry tub are code requirements by the Village.

•                     Battery operated faucets will allow for touchless use of the faucets, preventing contact from person-to-person.

•                     Staff had planned to reuse/relocated urinals, however, the urinals in place are outdated and in need of replacement.

•                     Electrical work was not included in the original contract. New NPOD-key switch (switch to turn the power on/off), demolition and relocations for new restroom configurations (fans, outlets, conduit/wiring) are required as shown in the permit drawings.

 

 

 

Financial Impact

The John Humphrey Complex Renovations (Design-Build) - Phase II was budgeted at $500,000 with a GMP awarded to V3 at $448,300.00 leaving $51,700 for unforeseen expenses. Funds are budgeted in account: 283-4003-443100 for this change order totaling: $12,610

 

 

 

Recommended Action/Motion

 

I move to approve the John Humphrey Complex Renovations (Design-Build) - Phase II Change Order