Title: /Name/Summary Verizon Wireless - 15501 Park Station Blvd. - Re-install equipment on water tank/Remove ballast frame temp tower
Attachments: 1. 2021.04.26 Structural Analysis Report for Verizon, 2. 2024.07.26 - CBBEL Approval L1.072324, 3. VZW PM - Rt 7 and West- Orland Park WT - Final CDs 042324.APPROVED. pdf
Date Ver.Action ByActionResultAction DetailsMeeting Details/Media Packet
No records to display.

Title/Name/Summary

Verizon Wireless - 15501 Park Station Blvd. - Re-install equipment on water tank/Remove ballast frame temp tower

 

History

QUICKFACTS

 

Project

Verizon Wireless - 15501 Park Station Blvd - Appearance Review

Legistar Case 2024-0487

AR-24-00442

 

Petitioner                      

Eric Lennington, Terra Consulting Group for Verizon

600 Busee Highway, Park Ridge IL 60068

 

Purpose

The purpose of this petition is to reinstall antennas and antenna related equipment onto the Water Tower #8, that were previously removed when the Village Water Tower was painted.

 

Requested Actions: Appearance Review

 

Project Attributes

Address: 15501 Park Station Blvd, Orland Park, IL 60467

 

P.I.N.(s): 27-17-401-004-0000

 

Parcel Size: 0.52 acres

 

Comprehensive Plan Planning District: Centennial

Comprehensive Land Designation: Community and Institutional

Existing Zoning: MFG Manufacturing

Existing Land Use: Village Water Tower

 

Surrounding Land Use:

North: Open Space and R-4 -Vacant and Sheffield Square

South: Open Space - Centennial Park West and Metra Parking Lot

East: Open Space - Metra Parking Lot

West: Open Space - Metra Parking Lot

 

 

PROJECT DESCRIPTION & CONTEXT

When Water Tower #8 was painted by Village, the petitioner relocated existing antennas and antenna-related equipment located on the water tower to a ballast framed temporary tower. Petitioner now intends to move the equipment from the temporary existing ground mounted ballast frame tower and re-install them on the water tower. The hybrid cables connecting the existing ground mounted equipment to the water tower will be routed via the existing underground conduits. The hybrid cables will then be routed up the tower interior to the proposed raycap junction boxes on top of the tower. The ballast frame temporary tower is to be removed in its entirety from the property, and the surrounding area to be restored to its former condition.

 

 

PLANNING OVERVIEW

The petitioner is proposing performing the following work on the ground and upon the existing tower located at 15501 Park Station Blvd.

 

TOWER MODIFICATIONS:

The proposed antennas and equipment mounts are to be installed on the Water Tower.

 

Proposed Final Verizon Antenna and Equipment Summary (RAD = 116’-0”)

•                     (6) Commscope NHH-65B-R2B

•                     (3) nL-Sub6 Antenna w/ Ericsson VZE01 RRU

•                     (3) RRU 8843

•                     (3) RRU 4449

•                     (3) HFT1206-24SV2-XXX Hybrid Cables

•                     (3) Raycap RC3DC-3315-PF-48

 

The following is a list of existing other carrier equipment located on the water tower, which are to remain.

•                     (5) airMAX AM-5AC21 (RAD = 115’-7”)

•                     (2) airFiber 24 (RAD = 115’-7”)

•                     (3) Dish (RAD = 114’-7”)

•                     (2) Yagi (RAD = 118’-0”)

•                     Small Beacon (RAD = 115’-0”)

•                     Whip (RAD = 123’-9”)

•                     Dipole (RAD = 123’-3”)

 

No new equipment to be added to the tower, and project scope is limited to reinstallation of the equipment that was temporarily relocated to the temporary tower.

 

GROUND MODIFICATIONS

Removal of existing ballast frame temporary tower and restoration of the surrounding area to its former condition.

 

 

ENGINEERING:

Christopher B. Burke Engineering Ltd. has reviewed and approved the engineering plans and structural analysis for the Verizon improvements to the water tower located at 15501 Park Station Blvd. The engineering plans prepared by Terra Consulting, bearing revision date of April 23, 2024; and Structural Analysis Report for Verizon (#187771) prepared by Krech Ojard & Associated, bearing revision date of April 26, 2021, was approved on July 23, 2024.

 

LANDSCAPING:

The Village requires incremental improvements in the form of landscaping that would meet the Code requirements prescribed in Section 6-305.  In this case the requirement is being met by the existing landscape screening around the ground equipment enclosure. Petitioner is to ensure that the landscaping is restored to its former condition.

 

 

Recommended Action/Motion
The Appearance Review for Verizon Wireless - 15501 Park Station Blvd - Reinstallation of Equipment on Water Tower project, case number 2024-0487, as depicted on Plans prepared by Terrra Consulting, bearing revision date of April 23, 2024; and Structural Analysis Report for Verizon (#187771) prepared by Krech Ojard & Associated, bearing revision date of April 26, 2021 has been administratively approved on July 26, 2024 subject to the following conditions:

 

1.                     The project will be in substantial conformance with the project documents listed above;

2.                     All Building permit requirements are met, and fees are paid at time of permit pick up;

3.                     Payment of the engineering review fees shall be paid in full at time of permit pick up;

4.                     Landscaping and opaque fences shall be used to screen any ground equipment and/or utility sub-stations;

5.                     No new equipment to be added to the tower - the project scope is limited to reinstallation of existing antennas and antenna-related equipment;

6.                     Remove the ballast frame temporary tower in its entirety from the property and restore the surrounding areas to their former condition;

7.   Pass all inspections by Orland Park Police Department and Orland Park Public Works Department.