File #: 2020-0456    Version: 0 Name: John Humphrey Complex Renovations (Design-Build) - Phase II Change Order
Type: MOTION Status: PASSED
File created: 6/29/2020 In control: Board of Trustees
On agenda: 7/6/2020 Final action: 7/6/2020
Title: John Humphrey Complex Renovations (Design-Build) - Phase II Change Order
Attachments: 1. JHC Renovations (Design Build) - Phase II Change Order, 2. Contract - Signed

Title

John Humphrey Complex Renovations (Design-Build) - Phase II Change Order

 

History

The Village of Orland Park awarded V3 Construction Group, LTD. the contract in accordance with their proposal submitted March 24, 2020, for Design-Build John Humphry Complex Renovations phase II to renovate the concession stand and restrooms for a Guaranteed Maximum Price of four hundred forty-eight thousand three hundred and no/100 ($448,300.00) dollars.

 

The Scope of Work includes:

                     Removal and replacement of existing roof;

                     Renovation of the women's restroom to meet generally accepted industry standards;

                     Renovation and expansion of the men's restroom, the number of stalls and sinks to meet generally accepted industry standards;

                     Renovation and conversion of the concession stand area to be an exterior service only stand.

 

V3 has submitted a change order (attached) for the following items:

                     Change from quarry tile floor to non-slip epoxy flooring to storage room and entry vestibule (185sf): $2,220

                     Mop sink and laundry tub in storage space (code requirement): $3,500

                     Battery operated faucets (2 per restroom): $2,600

                     Replacement urinals (3): $2,040

                     Electrical upgrades required to achieve the scope of the project: $8,250

Total of Change Order: $12,610

 

Staff seeks Board approval for these changes.

                     The mop sink and laundry tub are code requirements by the Village.

                     Battery operated faucets will allow for touchless use of the faucets, preventing contact from person-to-person.

                     Staff had planned to reuse/relocated urinals, however, the urinals in place are outdated and in need of replacement.

                     Electrical work was not included in the original contract. New NPOD-key switch (switch to turn the power on/off), demolition and relocations for new restroom configurations (fans, outlets, conduit/wiring) are required as shown in the permit drawings.

 

 

 

Financial Impact

The John Humphrey Complex Renovations (Design-Build) - Phase II was budgeted at $500,000 with a GMP awarded to V3 at $448,300.00 leaving $51,700 for unforeseen expenses. Funds are budgeted in account: 283-4003-443100 for this change order totaling: $12,610

 

 

 

Recommended Action/Motion

 

I move to approve the John Humphrey Complex Renovations (Design-Build) - Phase II Change Order