Title
143rd Street and LaGrange Road Improvement - ComEd Utility Relocation
History
Integral to the 143rd Street and LaGrange Road intersection improvements is the relocation of public utilities that are in conflict with the new roadway design and construction. Identified utilities that require relocation include facilities owned by Commonwealth Edison (ComEd), AT&T, Comcast and to a limited degree - Nicor. This item deals exclusively with the relocation and burial of electrical facilities owned by ComEd.

Since the early phases of design, the relocation of utilities has been a major critical-path component of every schedule that has been developed for this improvement. Over recent months, several property acquisition items have come to the Board for authorization as we have identified portions of properties along the intersection corridor that must be acquired for utility relocation work and roadway widening. Final property acquisition work continues as we move nearer to the advance utility relocation work and roadway construction.

As the overall budget for the 143rd Street and LaGrange Road project was formulated, ComEd was asked to provide a preliminary cost estimate and in August 2009, a figure of $6.1 million was provided as the potential cost to relocate and bury electrical lines on LaGrange Road from the Southwest Highway viaduct to generally 144th Street and on 143rd Street from generally John Humphrey Drive to the Metra tracks to the west. This was a very preliminary cost estimate, as design for the overall project had not yet proceeded to a point where finite utility needs could be defined with any degree of accuracy. Since then, Staff and engineers have continued to refine the overall project and have been able to get interim review approvals from IDOT to better define the scope of the improvement.

This past week, ComEd provided a written proposal to the Village dated July 19, 2010, for the costs associated with the relocation of the over...