File #: 2026-0563    Version: 0 Name: Ravinia Avenue South Extension Construction, Contract Award
Type: MOTION Status: IN COMMITTEE /COMMISSION
File created: 6/5/2026 In control: Committee of the Whole
On agenda: 6/15/2026 Final action:
Title: Ravinia Avenue South Extension Construction, Contract Award
Attachments: 1. Proposal Results
Title
Ravinia Avenue South Extension Construction, Contract Award

History
The Village issued RFP #26-037 for the Ravinia Avenue South Extension, Construction on May 1, 2026 to solicit proposals from qualified contractors for the construction of the Ravinia Avenue extension from Ravinia's current southern terminus to LaGrange Road.

Because a portion of the proposed roadway extension is located on right-of-way not currently owned by the Village, the RFP requested pricing under two scenarios:

Scenario 1 - Full Extension: Construction of the entire roadway extension assuming all required right-of-way is available at the time of construction.
Scenario 2 - Phased Construction: Construction of improvements within right-of-way currently owned by the Village with separate pricing for the portion of the project located on right-of-way not currently owned by the Village. The contract pricing will hold through December 31, 2029.

The RFP yielded one proposal from P.T. Ferro Construction Co.:

Scenario 1 - Full Extension: $3,484,548.48
Scenario 2 - Phased Construction: $3,763,258.10
Base Work: $3,001,007.66
Deferred Work: $762,250.44

Given that the right-of-way will be acquired via eminent domain and is unlikely to be settled this year, staff recommends entering into an agreement with P.T. Ferro Construction Co. under Scenario 2.

Financial Impact
This project is being funded through the proposed Village’s Tax Increment Financing (TIF) district.

Recommended Action/Motion
I move to recommend a contract with P.T. Ferro Construction Co. for "Scenario 2 - Base Work" in an amount not to exceed $3,001,007.66, plus a $300,000.00 project contingency, and as fully presented;

AND

Recommend a contract with P.T. Ferro Construction Co. for “Scenario 2 - Deferred Work" in an amount not to exceed $762,250.44, plus a $76,000.00 project contingency, and as fully presented.

(Full motion - not necessary to be read)

I move to recommend the execution of a Contractor Agreement bet...