Brentwood Park Renovation Contract Amendment
History
On August 6, 2018, the Board approved the contract with Innovation Landscape Inc. for the renovation of Brentwood Park in an amount not to exceed $170,152.06. The removal and the disposal of the asphalt from the two full-size basketball courts was not included in the contract, as staff was going to perform the work in-house. Staffing levels did not allow this to occur resulting in an increased cost of $5,400.
On October 1, 2018, this item was reviewed by the Parks & Recreation Committee, recommended for approval, and referred to the Village Board of Trustees for consideration.
Financial Impact
Funds are available in the Parks and Grounds accounts for FY2018.
Recommended Action/Motion
I move to approve an amendment for the additional specified work to the Brentwood Park Renovation project with Innovation Landscape Inc., of Oswego for an additional $5,400.00 for a total adjusted amount not to exceed $175,552.06.