File #: 2022-0060    Version: 0 Name: RFP 22-002 - CPAC Vertical Turbine Pump Replacement
Type: MOTION Status: PASSED
File created: 1/7/2022 In control: Board of Trustees
On agenda: 2/7/2022 Final action: 2/7/2022
Title: /Name/Summary RFP 22-002 - CPAC Vertical Turbine Pump Replacement
Attachments: 1. Proposal_Crossroads Construction, 2. Proposal_Robe Inc, 3. RFP 22-002 Audit Report, 4. RFP 22-002 Tabulation, 5. Signed Contract, 6. Addendum A-CPAC Vertical Turbine Replacement, 7. Robe, Inc - CPAC Vertical Turbine Pump Replacement, 8. Robe, Inc. - Change Order #1 - CPAC Vertical Turbine Pump Replacement
Title/Name/Summary
RFP 22-002 - CPAC Vertical Turbine Pump Replacement

History
RFP 22-002 CPAC Vertical Turbine Pump Replacement was issued on January 4, 2022, and closed on January 20, 2022. The project scope includes the replacement of the existing Vertical Turbine Pump Station #3 at the Centennial Park Aquatic Center (CPAC). The new turbine pump will be more efficient (96% vs 80%) than the existing pump, and require less maintenance overall.

Twenty-one (21) vendors fully or partially downloaded the RFP documents, and two (2) submitted proposals. It should be noted that courtesy emails with information regarding the RFP were sent to potential vendors in an effort to obtain as many submittals as possible. It should also be noted that the Village received only two (2) proposals for a similar turbine replacement project in 2021 from the same contractors as this time, suggesting that there are a limited number of contractors who are capable of performing this work. The RFP audit report and bid tabulation are attached for reference.

The original proposal price submitted by Robe, Inc. was $119,180.00, and $80,100.00 by Crossroads Construction. Due to the large difference between the proposal prices, the Public Works Department reached out to Robe, Inc. to confirm that its proposal reflected its best and final price. Robe subsequently submitted a revised proposal for $107,060.00, or a 10% reduction in price.

The final proposal totals are as follows:

Crossroads Construction, Inc.
Total Proposal Price - $80,100.00

Robe, Inc.
Total Proposal Price - $107,060.00

As an RFP, the Village evaluates proposals based on prices, vendor qualifications, and additional factors deemed relevant. The Village of Orland Park retains the right to accept any proposal, any part or parts thereof, or reject all proposals.

The Village has worked previously with Crossroads Construction, Inc., most recently in 2021 on the CPAC Stair and Landing Replacement project. The Village had nu...

Click here for full text