header-left
File #: 2018-0250    Version: Name: Orland Park Nature Center - Upland Design Inc. Additional Construction Observation Services
Type: MOTION Status: PASSED
File created: 4/2/2018 In control: Board of Trustees
On agenda: 5/7/2018 Final action: 5/7/2018
Title: Orland Park Nature Center - Upland Design Inc. Additional Construction Observation Services
Attachments: 1. EXTRA WORK AUTHORIZATION #3, 2. Upland Nature Center Contract
Title
Orland Park Nature Center - Upland Design Inc. Additional Construction Observation Services

History
Engineering addendum
Upland Design was contracted by the Village in February 2016 for a total of $62,761 to produce engineering and construction plans, bid documents and construction oversight for the Nature Center site improvements. The original contract included 24 construction observation visits.

Since that time, the following additional work has been authorized:
1) Extra Authorization #1: On September 6, 2016, the Open Lands Commission approved an additional $425 for Uplands Engineer to perform additional survey work that incorporated final IDOT grading along Lagrange Road.
2) Extra Authorization #2: On December 8, 2016, The Open Lands Commission approved an additional $5,100 to cover unanticipated floodplain modeling costs. On December 19, 2016, the Board of Trustees also approved the additional engineering services for $5100.
3) Extra Authorization #3: On December 12, 2017, the Open Lands Corporation/Commission approved up to $15,000 for additional construction observation visits. This item is now before the Village Board of Trustees for approval of up to $12,864 for 24 additional construction observation visits.

On December 18, 2017, the Village Board awarded the Orland Park Nature Center site improvements construction contract to Hacienda Landscaping, the (significantly) lowest bidder on the project. The IIIFFC (Indiana, Illinois, Iowa Foundation for Fair Contracting) filed a bid protest questioning the Hacienda bid. However, Hacienda has met Village bid requirements and the Village has no legal basis to deny them the award of the Nature Center project. The watchdog group is likely to visit and monitor the site during construction. During the Hacienda Development Services Committee meeting, discussion between the Committee members and staff supported the increase in the number of Upland Design's construction observations visits.

Other complexit...

Click here for full text